1. In order to properly use and maintain the operation of the cement curb stone machine equipment, the maintenance personnel must fully understand the performance and characteristics of the equipment, and do not operate at will, so as not to hurt people and damage the parts.
2. The user must carefully read this manual before installing and using the cement brick machine. If you have any questions, please contact our factory in time for consultation.
3. During inspection and maintenance, the main power supply should be cut off and a warning sign should be hung up.
4. The moving parts of this equipment should not be approached by non-workers during work.
5. Fully automatic cycle operation can only be performed when all parts are in the original position.
6. Non-computer control cabinet operators are not allowed to press the button at will, so as not to injure people and damage the machine.
7. After the end of each shift, the electrical switch should be in the "power off" or "stop" position.
8. The cement in the storage hopper should be used up in time to prevent solidification.
9. The electrical of the machine should be grounded reliably to ensure safety.
10. The selection of hard aggregate should be compatible with the holes on the side of the mold box, and hard foreign matter should not be mixed into the material to prevent damage to the cement brick machine mold.
11. At the end of forming, if the material is not enough, the indenter should not be pressed down to prevent damage to the indenter cylinder and the indenter synchronization structure, causing the indenter to be out of sync.
12. The solidified concrete on the pallet of the brick machine should be cleaned up in time.
13. Vibration molding time should be strictly controlled. If the molding time is long and the pressure head cannot be lowered, adjust the amount of feeding.
14. Check whether each travel switch of the cement brick machine is in place at any time. If it is loose, adjust it in time and tighten it. The distance between the end of the travel switch and the sensing block is 5-8mm to prevent damage.
15. The condenser on the hydraulic station must be used in summer, otherwise the oil will heat up and affect normal use. The oil should be refilled and replaced in time. The filter element should be replaced in time according to the instructions of the flood generator, otherwise it will cause the hydraulic system to malfunction.
16. Replace the rubber scraper on the feeding hopper in time and adjust the gap, otherwise the material will leak and the pressure head will stick to the material.
17. All bolts need to be tightened before use.
18. The upper plane of the vibrating platform, the board feeder, and the brick feeder must be flat, otherwise the pallet of the brick machine cannot be transported smoothly, and the blocks cannot be pushed out or cracked.
19. All lubrication parts need to be lubricated before each shift.
20. Clean up in time after each shift.
Whether it is for companies or users in the machinery industry, the safety of the machine is very important, and it is directly related to the personal safety of the staff. Especially for large-scale machinery and equipment, operators must comprehensively learn the operating points and strengthen their safety awareness before using them.