1. Construction survey lofting First, the facility control network was deployed, the construction stakeout was carried out, the segmented excavation stake number and the excavation contour line mark were buried, and the sections before and after the excavation were measured.
Determine the slope protection range line according to the measurement and lofting of the construction control network. Before cutting the slope, the beach terrain should be measured on the spot to determine the slope cutting range.
2.the slope is cleared
According to the requirements of the design drawings and the requirements of the supervision engineer, all turf, trees, roots and debris are removed and transported within the scope of the project implementation. The topsoil and turf on the original ground should be as deep as shown in the drawings and required by the supervision engineer. After the surface soil is removed, if wells, tombs, tree stumps, pits and animal nests are still found, they must be disposed of. The quality of the backfill should be approved by the supervising engineer. Filling requires backfilling treatment, and the clearing is carried out with a 1m3 backhoe excavator, which is pushed by a 74kw bulldozer to the spoil area for flattening.
3.the whole slope
After the foundation is cleared, the slope protection earthwork can be excavated and repaired. First, the line is laid out according to the design requirements. The excess earthwork is excavated with a 1m3 backhoe excavator, and then transported to the bund of the embankment with a 74kw bulldozer. No more than 2m. When performing mechanical slope cutting, a 10cm thick protective layer is reserved above the foundation surface. The protective layer is manually excavated before the construction of the upper dry stone slope protection and transported to the spoil area by a 1t motorized dump truck.
For the part that needs to be filled, the slope-cutting earth is used for backfilling. When backfilling, it is carried out in layers with steps. It cannot be paving along the slope. Large-area backfills are backfilled and compacted in layers with a 74kw bulldozer. The thickness of each layer is less than 30cm and cannot be used locally. The mechanical backfilling part is manually backfilled and compacted with a frog rammer, and the thickness of each layer is less than 10cm.